Week 24 – 11th to 15th January 2016

Maddomswood Barn Conversion

This week has been very busy and next week will be even busier.

Trades on site:

Next week we will be joined by Steven Cassam and Adam Porter of S & A Plastering and Building. They will be carrying out the Plasterboard tacking and Plastering plus the Hardwall Plaster to the new block work walls, the specialist fire rated plaster to the fire surround and the tape and filling of the joints to the plasterboard fixed to the external oak structure.

 

We have hit programme this week which is great. All trades have worked hard and diligently. I have rewarded them with of course their wages plus Costa coffee and the odd cake! Happy site Happy Life…

Andy, Joe and Alex finished fixing the 100mm insulation, counter batten, sprockets and membrane to the external skin plus some other fiddly jobs inside the barn in preparation for the arrival of S & A Plastering on Monday the 25th of January.

NOTE: We had intended on using the same 200mm Helitie that was used on the warm roof to secure the insulation to the structure; however Andy did not feel that they secured the boards to the structure sufficiently due to the vertical installation. There was too much wobble and with the extra weight of the Oak weatherboarding there was a danger that the insulation boards/batten could work loose. The Helities are designed for warm roofs where the installation is at an angle. The solution was that e used the Helitie to fix the boards in place and then went around again and used 200mm screws to securely fix the boards to the oak studs through the counter batten.

 

Maddomswood Historic Oak Barn Conversion East Sussex - 100mm Insulation fixed to the external elevations - insulation tape has been used to cover any joints

100mm Insulation fixed to the external elevations – insulation tape has been used to cover any joints

 

Maddomswood Historic Oak Barn Conversion East Sussex -

An eaves vent serving one of the 1st floor bedrooms

 

Maddomswood Historic Oak Barn Conversion East Sussex - The sprockets fixed to the counter battens at low level prior to the installation of the 200mm oak weather board cladding

The sprockets fixed to the counter battens at low level prior to the installation of the 200mm oak weather board cladding

 

Maddomswood Historic Oak Barn Conversion East Sussex - Membrane fixed to the counter batten over the 100mm insulation

Membrane fixed to the counter batten over the 100mm insulation

 

Paul and Shane from Electricare Ltd finished the 1st fix electrical installation in the Barn and Side Extension. The cables for the Milking Parlour have been left coiled up outside the side the Main Entrance door ready to be laid in conduits underground  once the scaffold has been struck.

 

Maddomswood Historic Oak Barn Conversion East Sussex - The 1st fix electric installation cables ready to be installed within the consumer unit during 2nd fix

The 1st fix electric installation cables ready to be installed within the consumer unit during 2nd fix

 

Maddomswood Historic Oak Barn Conversion East Sussex - Milking Parlour services leaving the Barn via the Main Entrance

Milking Parlour services leaving the Barn via the Main Entrance

Tom and Jack from TPS Plumbing and Heating have been working to finish the installation of the foul drainage and hot and cold plumbing to the Shower Rooms, Utility , Kitchen and Master Bedroom Bathroom. As with the electricians they have left all the pipes for the Milking Parlour coiled up outside the main entrance door ready to be laid underground once the scaffold is struck. Next week they will be laying out the Under Floor Heating system prior to the 75mm screed.

 

Maddomswood Historic Oak Barn Conversion East Sussex - Utility room foul drainage pipe ready to be insulated and then covered with 75mm screed

Utility room foul drainage pipe ready to be insulated and then covered with 75mm screed

 

Maddomswood Historic Oak Barn Conversion East Sussex - The underfloor heating and plumbing pipes ready to be connected to the UFH manifolds, hot water tank and boiler

The underfloor heating and plumbing pipes ready to be connected to the UFH manifolds, hot water tank and boiler

 

Maddomswood Historic Oak Barn Conversion East Sussex - The Hot and Cold water and foul drainage pipe for the sink within the Kitchen Island

The Hot and Cold water and foul drainage pipe for the sink within the Kitchen Island

 

Maddomswood Historic Oak Barn Conversion East Sussex - The Gas service pipe for the gas hob and the electric cable in ducting for the Island Dishwasher

The Gas service pipe for the gas hob and the electric cable in ducting for the Island Dishwasher

 

Maddomswood Historic Oak Barn Conversion East Sussex - The gas service pipe, 50mm kitchen drainage pipe and conduits for the water pipe and electric cables fixed to the floor prior to being covered with Damp Proof Membrane, 100mm Insulation and 75mm of screed.

The gas service pipe, 50mm kitchen drainage pipe and conduits for the water pipe and electric cables fixed to the floor prior to being covered with Damp Proof Membrane, 100mm Insulation and 75mm of screed.

 

Tony and Danny from Old Town Roofing have this week finished the Main Barn roof including most of the Cast Iron Gutter supplied by the Cast Iron Superstore. They have made a start on the Milking Parlour which will be completed next week leaving just the side extension to be finished when the scaffold is struck; the low level scaffold beams are in the way.

 

Maddomswood Historic Oak Barn Conversion East Sussex - The completed cat slide roof to the SE Elevation

The completed cat slide roof to the SE Elevation

 

Maddomswood Historic Oak Barn Conversion East Sussex - The completed roof to the NW Elevation

The completed roof to the NW Elevation

 

Maddomswood Historic Oak Barn Conversion East Sussex - The cast iron gutter installed to the NW Elevation

The cast iron gutter installed to the NW Elevation

 

Maddomswood Historic Oak Barn Conversion East Sussex - The cast iron gutter installed to the NW Elevation

The cast iron gutter installed to the NW Elevation

 

Maddomswood Historic Oak Barn Conversion East Sussex - Tiles loaded out on the Milking Parlour

Tiles loaded out on the Milking Parlour

 

Category: Construction Phase, Maddomswood Barn, My Projects, Property Developing

About the Author ()

Leave a Reply

Your email address will not be published. Required fields are marked *