RSSMy Projects

29 – Barn Conversion – Week 24

29 – Barn Conversion – Week 24

| 20th January 2016 | 0 Comments

  Week 24 – 11th to 15th January 2016 Maddomswood Barn Conversion This week has been very busy and next week will be even busier. Trades on site: Andy Feaver, Joe and Alex from Feaver Carpentry and Construction Paul and Shane from Electricare Ltd Tom Sutton and Jack of TPS Plumbing and Heating Tony, Danny and […]

Continue Reading

28 – Barn Conversion – Week 23

28 – Barn Conversion – Week 23

| 10th January 2016 | 0 Comments

Week 23 – 4th to 8th January 2016 Maddomswood Barn Conversion HAPPY NEW YEAR It had been 16 days since the site had been open; the contractors had enjoyed their holiday but it was time to get back to work. Andy, Joe and Alex arrived at 0730. They were joined by Tom Sutton of TPS Plumbing […]

Continue Reading

27 – Barn Conversion – Weeks 21& 22

27 – Barn Conversion – Weeks 21& 22

| 21st December 2015 | 0 Comments

Weeks 21 and 22 – 7th to the 18th of December Maddomswood Barn Conversion   I am writing this post on the 21st of December; Its a bit late!!   I haven’t had a chance to write anything for 2 weeks as the site has been very busy. Not only have the Old Town Roofing been hard […]

Continue Reading

26 – Barn Conversion – Week 20 – part 2

26 – Barn Conversion – Week 20 – part 2

| 3rd December 2015 | 0 Comments

Week 20 – 30th November to – 4th of December Part 2 – Wednesday, Thursday and Friday Barn  Conversion Wednesday The barn conversion continues…..The roofers weren’t on site today…they had to finish another job. This is fine. They are on a price and as long as they finish boarding the roof by the end of the […]

Continue Reading

25 – Barn Conversion – Week 20 – Part 1

25 – Barn Conversion – Week 20 – Part 1

| 1st December 2015 | 0 Comments

Week 20 –  30th November to – 4th of December Part 1 – Mon & Tuesday Barn Conversion Monday This is a great day….today the roofers arrive and we can finally start to close in the barn structure and take one step further to being water tight. Also the Tanking to the side extension will commence. Nick […]

Continue Reading

24 – Barn Conversion – Week 19

24 – Barn Conversion – Week 19

| 30th November 2015 | 0 Comments

Maddomswood Barn Conversion Week 19 – 23rd – 27th of November This week on the barn conversion Danny will be finishing the facing brickwork to the dwarf walls and will make a start on building up the brickwork between the rafters to the south east elevation out-shuts. He also will build the block wall that separates […]

Continue Reading

Crouch Cottage – Grade 2 Listed Cottages – Wadhurst

Crouch Cottage – Grade 2 Listed Cottages – Wadhurst

| 26th November 2015 | 0 Comments

Conversion of Two Grade 2 listed cottages with no mod cons into one 4 bedroom house with a 6 x 4 kitchen extension These grade 2 listed cottages came onto the market when we were not ready to purchase so with regret we set aside the advert. This type of project is rare and getting rarer all […]

Continue Reading

23 – Barn Conversion – Week 18

23 – Barn Conversion – Week 18

| 16th November 2015 | 0 Comments

Week 18 – 16th – 20th of November Barn Conversion Monday I arrived at 7.00am this morning to make final preparations for the concrete pour for the barn slab. The over site had been prepared but there were some dips that needed to be filled with broken tiles. NOTE: Concrete costs a lot of money. The rate I was paying […]

Continue Reading

22 – Barn Conversion – Week 17 part 2

22 – Barn Conversion – Week 17 part 2

| 13th November 2015 | 0 Comments

Week 17 – 9th – 13th of November Barn Conversion – Wednesday to Friday   Wednesday The mini digger is off hired and is replaced by a 4 ton digger. We ordered a 3 ton digger but a 4 ton was sent for the same price as a 3 ton. Good news. By the end of […]

Continue Reading

21 – Barn Conversion – Week 17 part 1

21 – Barn Conversion – Week 17 part 1

| 9th November 2015 | 0 Comments

Week 17 – 9th – 13th of November Barn Conversion – Monday and Tuesday Last weekend was busy as you will have read in the previous post; all the Oak structure and brickwork was cleaned along with the trusses in the side extension and milking parlour. Once cleaned by BR Holland , Nick Teasel from South […]

Continue Reading