Tag: barn conversion

34 – Landscaping, Plastering & much more

34 – Landscaping, Plastering & much more

| 27th February 2016 | 0 Comments

Landscaping, Plastering, 2nd Fix Electrics and Carpentry Maddomswood Oak Barn Conversion Weeks 29 & 30…. 15th to 26th of February   During this fortnight much work has taken place. The plastering, carpentry and second fix electrics have nearly been completed  in the Barn and Milking Parlour and outside the Landscaping of the garden and paddock started.   Landscaping John […]

Continue Reading

33 – Plastering, Roofing & Much More

33 – Plastering, Roofing & Much More

| 14th February 2016 | 0 Comments

Plastering, Windows, Roofing and General 1st Fix Carpentry Maddomswood Oak Barn Conversion Weeks 27 & 28…. 1st to 12th of February In this post I have combined weeks 27 and 28 as much of the Carpentry and Plastering has been steadily completed across the 10 working days. Roofing This week we said goodbye to Tony and […]

Continue Reading

21 – Barn Conversion – Week 17 part 1

21 – Barn Conversion – Week 17 part 1

| 9th November 2015 | 0 Comments

Week 17 – 9th – 13th of November Barn Conversion – Monday and Tuesday Last weekend was busy as you will have read in the previous post; all the Oak structure and brickwork was cleaned along with the trusses in the side extension and milking parlour. Once cleaned by BR Holland , Nick Teasel from South […]

Continue Reading