23 – Barn Conversion – Week 18

23 – Barn Conversion – Week 18

| 16th November 2015 | 0 Comments

Week 18 – 16th – 20th of November Barn Conversion Monday I arrived at 7.00am this morning to make final preparations for the concrete pour for the barn slab. The over site had been prepared but there were some dips that needed to be filled with broken tiles. NOTE: Concrete costs a lot of money. The rate I was paying […]